How to run a development appraisal, step by step
A residual development appraisal tells you what you can pay for a site. The ten steps in order, a worked example for eight houses, and the sensitivities.
You have found a site and need to know what to offer. A residual development appraisal answers that. Start with what the finished homes will sell for, take off every cost of building and selling them and the profit you need, and what is left is the most you can pay for the land. Here is the method in order for a small residential scheme in England, with a worked example.
What the residual method answers
Gross development value (GDV) minus total development cost minus developer's profit equals residual land value. Land is the balancing item, so it absorbs every error in the other inputs.
Turn it round and it answers the sibling question. If the land is already priced, at an asking price or an auction guide, hold the land cost fixed and solve for profit instead. The question then is whether that profit, on GDV or on cost, is enough for the risk and for a lender.
The ten steps in order
- Establish the scheme. Fix the units, the mix and the areas. Gross internal area (GIA) drives build cost. Net saleable area drives revenue. The ratio of net to gross is the efficiency: close to 100% for houses, often 75 to 85% for flats. A poor efficiency hurts twice, because you pay to build space you cannot sell.
- Gross development value. Price each unit from comparable new-build sales nearby, as a price per square metre or per square foot applied to your net areas. Use completed new-build sales, not second-hand stock, and check the dates. Value any affordable share at the price a registered provider will pay (the transfer value), usually well below open market value. See how to calculate GDV.
- Build cost. For a first pass use published benchmark rates per square metre of GIA, such as BCIS, adjusted for region and specification. Before you bid, get a cost plan from a quantity surveyor. Add external works (roads, drainage, landscaping), which benchmark rates exclude, and any abnormals: demolition, contaminated ground, piling, utility connections. Brownfield land carries most of these, and they are the usual reason a bid proves too high.
- Professional fees. Architect, engineers, planning consultant, quantity surveyor, building control and warranties. Typically 8 to 12% of build cost, higher for small or complex schemes.
- Contingency. Typically 5 to 10% of build cost. Use the lower end with a firm cost plan and a ground investigation, the higher end with neither.
- Planning costs, Section 106, CIL and biodiversity net gain. Section 106 pays for infrastructure and, on larger schemes, affordable housing; outside designated rural areas it is not usually sought below ten units. Community Infrastructure Levy, where charged, is a fixed rate per square metre of new floorspace. As of October 2026 most new schemes in England must also deliver a 10% biodiversity net gain. Check current rates and thresholds with the local authority; our planning use case shows what to look for.
- Finance. Interest is charged on the balance actually drawn, not the whole facility. The cost depends on the rate, arrangement and exit fees, the drawdown profile (build spend is slow at the start and the end) and how long the debt stays out while the units sell.
- Marketing, agents and legal on sales. A show home or CGIs, portal listings, the selling agent's fee and conveyancing. Around 2 to 3% of GDV.
- Developer's profit. Commonly 15 to 20% of GDV, or 20 to 25% on cost, higher for riskier schemes. Lenders set their own floor and will not usually fund below it, because the profit is also their cushion if sales disappoint.
- Residual land value, then acquisition costs. Subtract everything above from GDV. Out of that gross residual come Stamp Duty Land Tax, legal, survey and agent's fees on acquisition, and interest on the land itself. What is left is your bid.
Static residual or cashflow appraisal
A static residual treats the scheme as if everything happens at once. Finance is a rule of thumb, for example interest on the full build cost for half the build period, plus the whole balance over the sales period. Fine for a first screen.
A cashflow appraisal lays the same costs and revenues out month by month, with interest on the balance drawn and rolled up. It shows peak debt, which decides how much equity you need and whether a lender's loan-to-cost limit bites. Run the cashflow before you exchange. The static finance figure is almost always optimistic on a long programme.
Sensitivity
Because land is the residual, it is highly geared to every other input. Run at least these before you bid:
- Sales prices 5% and 10% lower.
- Build cost 10% higher, with fees and contingency following it.
- Programme six months longer, which adds interest on the whole drawn balance each month.
- The three together, as a downside case.
If the downside case shows no profit at the price you are about to pay, you are buying the vendor's land risk, not a development.
The viability test is not your bid
Planning viability uses the same arithmetic for a different purpose. When an applicant argues that a scheme cannot afford the obligations the plan asks for, the council tests it against a benchmark land value. Under national planning practice guidance on viability, as at October 2026, that benchmark is the site's existing use value plus a premium for the landowner, not the price paid and not a market bid.
Bid above the benchmark and that is your decision; you cannot later plead unviability. Build your bid on policy-compliant obligations from the start. A residual that only works with the affordable housing negotiated away is not one you can bank.
A worked example (illustrative)
Eight three-bedroom houses on a cleared plot, each about 1,000 square feet (93 square metres). Figures are round and illustrative.
- GDV: 8 houses at £400,000, from new-build comparables at around £400 per square foot. £3,200,000.
- Build: 8,000 square feet of GIA at £200 per square foot (about £2,150 per square metre), including external works. £1,600,000.
- Professional fees at 10% of build: £160,000.
- Contingency at 5% of build: £80,000.
- Planning, Section 106 and CIL: £120,000. No affordable housing below ten units.
- Sales and marketing at 2% of GDV: £64,000.
- Finance, interest and fees over roughly a year of build and a short sales period, on costs excluding land: £140,000.
- Developer's profit at 20% of GDV: £640,000.
Total costs excluding land: £2,804,000. Residual land value: £3,200,000 less £2,804,000, which is £396,000 before Stamp Duty Land Tax and acquisition fees. Profit of £640,000 on a total cost including land of £2,560,000 is 25% on cost.
Sensitivities:
- Sale prices 5% lower. GDV £3,040,000, sales costs £60,800, profit £608,000. Residual about £271,000. A 5% price move removes almost a third of the land value.
- Build costs 10% higher, with fees and contingency following. Build £1,760,000, fees £176,000, contingency £88,000. Residual about £212,000.
- Sale prices 10% lower leaves about £146,000.
At a £450,000 asking price instead, profit is about £586,000, 18% of GDV, falling to 12 to 14% under either sensitivity. That is the conversation the appraisal is for.
Doing this in MarketCode
MarketCode puts the evidence for the GDV and the planning line on one map. HM Land Registry sold prices for England and Wales flag new-build sales, and the matched energy certificate gives a floor area, so you can read recent new-build prices per square metre nearby, with dates. The site's planning history and constraints (England only) sit on the same view, and the ownership records show when a company holds the title, the start of land sourcing.
What MarketCode does not do today is run the residual for you. The Appraisal product has two parts. The Project appraisal, for an existing building, is available on invitation now for refurbishments in England and Wales. The Site appraisal, for new development, is coming next, England first: from your architectural plans as a PDF it will run the method above on the site's own evidence and show its reasoning line by line, so you can argue with any input. Until then, take the comparables and constraints into your own spreadsheet and keep the sensitivities. For how an appraisal should work when the evidence is live rather than typed in, read development appraisal for the AI era.
Keep reading: Development appraisal for the AI era, Gross development value: what it is and how to calculate it and How to assess planning risk on a development site.
Related guides
- Development appraisal for the AI eraThe residual method hasn't changed. What changes is who checks the inputs: spreadsheets, appraisal software, and what an AI agent adds to an appraisal.
- Permitted development rights: what you can build without planning permissionWhat the General Permitted Development Order lets you build in England without an application, the limits for extensions and conversions, and what removes them.
- Comparable evidence in property valuationHow valuers rank, adjust and weigh comparable sales in England and Wales, with a worked two-bed flat example and the traps in Price Paid and listing data.