The construction cost index, how each region compares with the national average, and the on-costs a scheme carries.
Tender prices
Residential tender prices are +2.9% over the year and +30% over five years (index 197.4694, 2026Q2). Building in Greater London costs 25% above the national average; in South East England 10% above.
Construction costs by region
| Region | Factor | Against the national average |
|---|---|---|
| Greater London | 1.25 | 25% above |
| South East England | 1.10 | 10% above |
A factor of 1.12 means building here costs 12% more than the national average.
What a scheme carries on top
| Item | Low | Mid | High |
|---|---|---|---|
| CONTINGENCY | 7.5% | 10% | 15% |
| OH_PROFIT | 8% | 10% | 15% |
| PRELIMS | 10% | 12% | 15% |
| PROF_FEES | 8% | 12% | 18% |
| Total, mid | — | 44% | — |